Building permit times in Austin Council District 10

New-home permits in Council District 10 took a median 83 days from application to permit in the last 22 months, number 6 of 10 among Austin's council districts.

Wait by type of job

Jobs with fewer than 20 permits in the district are left out.

New homes, year by year

Year issuedPermitsMedian days
202152175
2022373122
2023268110
202426691
202531280

District is the City's current council district for each permit's location. Compare every district or read how the numbers are computed.

Questions

How long does a building permit take in Austin District 10?

New-home permits took a median of 83 days in the last 22 months; the slowest tenth took more than 331 days. The table above shows other job types.