How long a commercial remodel or finish-out permit takes
Calendar days from application to issued permit. The fastest tenth of permits were issued within 6 days; the median was 55; one in ten took more than 323. The difference is mostly the lot and the applicant: what the site triggers and how complete the first submittal is.
By council district
District 10 was the fastest (median 36 days) and District 9 the slowest (70 days). Districts with fewer than 20 permits are left out.
| District | Permits | Median days | Slowest tenth over |
|---|---|---|---|
| District 10 | 554 | 36 | 131 |
| District 4 | 568 | 42 | 247 |
| District 6 | 284 | 43 | 152 |
| District 8 | 401 | 46 | 260 |
| District 5 | 260 | 48 | 211 |
| District 7 | 667 | 56 | 214 |
| District 2 | 394 | 57 | 221 |
| District 1 | 374 | 58 | 226 |
| District 3 | 455 | 60 | 286 |
| District 9 | 1,297 | 70 | 924 |
Year by year
| Year issued | Permits | Median days | Slowest tenth over |
|---|---|---|---|
| 2021 | 2,400 | 64 | 308 |
| 2022 | 2,669 | 73 | 297 |
| 2023 | 2,630 | 74 | 351 |
| 2024 | 2,719 | 55 | 360 |
| 2025 | 2,911 | 53 | 336 |
What slows it down
Site conditions such as floodplains, creek setbacks, historic districts, protected trees and drinking water protection zones add reviews. A readiness check tells you which apply to your lot.
What you need to submit
The core of the submittal for a commercial remodel or finish-out in Austin. Your lot can add items, for example a tree survey or floodplain documents; a readiness check lists them.
- Site plan or plot plan: setbacks, easements, existing and proposed structures
- Boundary survey: by a Texas registered professional land surveyor
- Sealed construction documents: architect and engineer sealed, including MEP
- Impervious cover calculations: existing and proposed, against the zoning and watershed limits
- Energy code compliance: Austin Energy Green Building / IECC documentation
Dirt to Permit is not the City of Austin. Confirm every requirement with the City's Development Services Department. How these numbers are computed.