Building permit times in Austin Council District 2

New-home permits in Council District 2 took a median 27 days from application to permit in the last 22 months, the fastest among Austin's council districts.

Wait by type of job

Jobs with fewer than 20 permits in the district are left out.

New homes, year by year

Year issuedPermitsMedian days
202187330
202292227
202351240
202468434
202562027

District is the City's current council district for each permit's location. Compare every district or read how the numbers are computed.

Questions

How long does a building permit take in Austin District 2?

New-home permits took a median of 27 days in the last 22 months; the slowest tenth took more than 96 days. The table above shows other job types.