Building permit times in Austin Council District 6

New-home permits in Council District 6 took a median 112 days from application to permit in the last 22 months, number 9 of 10 among Austin's council districts.

Wait by type of job

JobPermitsMedian days, District 6Median days, citywide
New homes (1–2 units)6411257
Residential additions and remodels1707068
Commercial remodels and finish-outs2844355
New commercial buildings2172121

Jobs with fewer than 20 permits in the district are left out.

New homes, year by year

Year issuedPermitsMedian days
202113238
20226369
20234973
20244089
202532134

District is the City's current council district for each permit's location. Compare every district or read how the numbers are computed.

Questions

How long does a building permit take in Austin District 6?

New-home permits took a median of 112 days in the last 22 months; the slowest tenth took more than 421 days. The table above shows other job types.